RS Mata Achmad Wardi × MATW

2026 Cataract Surgeries

FA# IND24035/PTR/EYE · 1 Aug 2026 – 31 Dec 2026

Data as of 19 Oct 2026, 11:43 WIB
Surgeries completed
139 / 300
On track
46.3% of target · 126 patients (some had both eyes operated)
Remaining surgeries
161
73 days left (64 working days)
Required pace
2.5/day
to finish by 31 Dec 2026
Actual pace
2.6/day
last 30 days · 3.5/day last 7 days
Projected completion
31 Dec 2026
at the 30-day pace
Funds utilised: AUD 16,680 of AUD 36,000 (139 × AUD 120)

Cumulative surgeries vs target

Surgeries per week

Patient pipeline

Operated139
Scheduled (upcoming date)3

Operated patients — demographics

Per patient (n = 126)

Sex
Male44
Female70
Age group
< 401
40–495
50–5930
60–6936
70+14

Patients without recorded age/sex are not counted.

Visual outcome (operated eye)

WHO categories. Post-op = latest recorded (day 4–8, otherwise day 1). 58 of 64 eyes with both measurements improved.

Before surgery (n = 101)
Good (≥ 6/18)5 (5%)
Borderline (6/24–6/60)37 (37%)
Poor (< 6/60)59 (58%)
After surgery (n = 64)
Good (≥ 6/18)40 (63%)
Borderline (6/24–6/60)22 (34%)
Poor (< 6/60)2 (3%)

Screening sites in Banten

14
screening events
13
locations
3
regencies/cities
  1. 1 Kec. Mancak · Kab. Serang 11 Aug 2026, 26 Aug 2026
  2. 2 Kec. Cinangka · Kab. Serang 13 Aug 2026
  3. 3 Kec. Tirtayasa · Kab. Serang 20 Aug 2026
  4. 4 Kec. Munjul · Kab. Pandeglang 30 Aug 2026
  5. 5 Kec. Cikande · Kab. Serang 9 Sep 2026
  6. 6 Desa Bumijaya · Kab. Serang 14 Sep 2026
  7. 7 Desa Lempuyang, Kec. Tanara · Kab. Serang 16 Sep 2026
  8. 8 Desa Dukuh, Kec. Kragilan · Kab. Serang 21 Sep 2026
  9. 9 Kec. Ciruas · Kab. Serang 23 Sep 2026
  10. 10 Kec. Cikeusal · Kab. Serang 30 Sep 2026
  11. 11 Kec. Walantaka · Kota Serang 3 Oct 2026
  12. 12 Kec. Baros · Kab. Serang 7 Oct 2026
  13. 13 Desa Ketos, Kec. Kibin · Kab. Serang 14 Oct 2026

Not yet mapped: Ciremen, Serang, Tambak, Serang

One marker per village/district; number = order of first visit. Coordinates: © OpenStreetMap; boundaries: geoBoundaries (CC BY 4.0).

Latest activities

View gallery →

Milestones

  1. 3 Jun 2026
    First contact with MATW
  2. 6 Jun 2026
    First meeting & offering letter sent
  3. 30 Jun 2026
    Compliance onboarding completed
  4. 8 Jul 2026
    Funding Agreement finalised
  5. 1 Aug 2026
    Program start
  6. 7 Aug 2026
    Funds received
  7. 12 Aug 2026
    MATW team site visit (screening, surgery, D1 follow-up)
  8. 31 Dec 2026
    Program end & final report
  9. 30 Jan 2027
    Acquittal Report due (≤ 30 days after completion)

Reporting

  • Interim progress reportDue 31 Oct 2026 Pending
  • Final reportDue 15 Jan 2027 Pending
  • Acquittal Report FormDue 30 Jan 2027 Pending